Technical Scoping and Sequencing
Discovery produced a long wish list: all 40 carriers, every kind of charge, a review screen, writing results back into the TMS, monthly reports and, as Meera's late addition, warehouse invoices. The pilot has eight weeks. You cannot do all of it, and the order you work in matters as much as the list itself.
The rule
Thin slice end to end first; riskiest and slowest things earliest.
- A thin slice is one narrow path through every layer of the system: mailbox → reading the invoice → matching it to a shipment → checking the rate → review screen. Do it for one carrier and one or two kinds of charge. Building layer by layer (perfect invoice reading for all 40 carriers before any matching) hides integration surprises until week seven.
- Riskiest first. Ask what could sink the pilot. At Harbourline it is this: can an invoice be matched to its shipment at all? If invoices do not reliably carry the lorry receipt (LR) number, the consignment number that also appears in the TMS, the whole plan changes. Test it in week one on 200 real invoices.
- Slowest first. Some work is mostly waiting: database credentials that need a security review, a VPN account, a firewall change. These take calendar time you do not control, so request them on day one.
- Write down what is out. A scope with an explicit "not in this pilot" list gives everyone something to point back to when new ideas arrive.